Tag Archive : Vale

Vale, Parauapebas: we are in the field

Technicians from IEME Brasil and LAEDE are in the field to carry out detailed inspection services in 16 special works of art (bridges or viaducts) and 7 tunnels of the Structural Integrity Management subordinated to the Directorate of Base Metals Atlântico Sul, of Vale, in Parauapebas (PA). The OAE and tunnels are located in the territories of Mineração Onça Puma, Mina do Salobo, Mina do Sossego and Porto São Luiz, in the States of Pará and Maranhão.

The contract began in August 2022 and is expected to end in September 2024. IEME estimates that approximately 30% of the service has already been completed.

Detailed inspection services for OAE and tunnels follow ABNT NBR 9452 – Inspection of Bridges, Viaducts, Concrete Walkways – Procedures and include the following tests:

  • Verification of corrosion potential
  • Checking the electrical resistivity of concrete
  • Sclerometry (NBR-7584) – By tested area
  • Chloride ion content
  • Sulphate content
  • RAA (Alkali Aggregate Reaction)
  • Weld penetrant liquid
  • Ultrasound
  • Infrared thermography
  • Pacometry
  • Concrete permeability
  • Concrete strength – core extraction
  • Extensometry test
  • Mapping with aerometry (drone)
  • Mapping using 3D scanning

The inspection results in detailed reports containing all the reports of the technological tests carried out, informing the state of conservation and any pathologies identified, reporting points of improvement, drawings with the repairs to be made, if the inspection defines it, and the classification grade of each asset , as required by the standard.

20230406_01_700x500

Carrying out the load test on the Itacaiúnas Bridge, using loaded trucks

20230406_02_700x500

Top and bottom view of the Itacaiúnas Bridge

20230406_03_700x500
20230406_04_700x500

Extraction of the specimen with the CP extracted

20230406_05_700x500
 
 
  • 20230406_01_700x500
  • 20230406_02_700x500
  • 20230406_03_700x500
  • 20230406_04_700x500
  • 20230406_05_700x500

Inspections of Vale’s Bridges in Marabá (PA)

Since last year, our Engineering team has been involved in services in the region of Marabá (PA). The target of the work is two Vale bridges. One is over the Tocantins River. Another, over the Jacundá River.

The railroad bridge over the Tocantins River, with its 2,340 m in length, is the main link between the center of Marabá and the peripheral districts. In addition, the bridge is crossed, in its central part, by the Estrada de Ferro Carajás, which serves the transport of cargo and passengers between the states of Pará and Maranhão.

Detailed inspection services are being carried out on the bridge in accordance with ABNT NBR 9452 – Inspection of Bridges, Viaducts, Concrete Walkways – Procedures, as well as the inspection of its metallic structure, considering non-destructive and destructive tests. Two prominent points in this work are the use of drones and 3D modeling. Drones, unmanned vehicles, are strategic for starting work, as they allow a first mapping of anomalies through photos. Thus, it is possible to select the points that need to be investigated further. We hired Dronus, which used Phantom and Matrice drones. The latter was essential as it has the ability to access the bottom of the board. The results of the field and drone inspections are being modeled in 3D using Revit software to graphically show the status of the work.

The Railway Bridge over the Jacundá River is close to the Mãe Terra indigenous reserve area. This bridge is also crossed by the Carajás Railroad. The work has a reinforced concrete structure approximately 180 meters long, which was the target of an intentional explosion in mid-2016. The following year, it was repaired and structurally reinforced.

In this bridge, the scope is based on the execution of instrumentation, numerical modeling of the structure by finite elements, analysis and interpretation of the instrumentation results and the numerical model, with the objective of defining the structural integrity, remaining useful life and safety coefficient of each structural element for the actual and projected loading of the Bridge. To facilitate access for bonding the extensometers, the solution was to hire and train climbers.

According to the Work Coordinator, Daniela David, there were many challenges to be overcome, but with the support of the entire team and the search for innovative solutions, it is possible to develop work with consistent results and that will facilitate the planning and execution of new services.