2014 World Cup


  • Cliente :Prefeitura de São Paulo
  • Cidade :São Paulo
  • Ano :2014
  • Projeto :Arena Corinthians

Arena Corinthians under inspection

The safety of Arena Corinthians, the opening stage of the 2014 World Cup, was evaluated by our team through a forced vibration test. For this, Vibrodina was used, mechanical generator equipment that simulates the movement of fans on the stands. In this way, it was possible to evaluate the dynamic behavior and find out if the structure was adequate in terms of safety and comfort parameters so that everything went well at the beginning of the Cup.

 

See below the article by Máquina do Esporte – 02/05/2013.

IEME Brasil evaluates the security of Arena Corinthians

7.-MaqEsporte_Mai_13